Assessment Year | 2001 |
---|---|
Principal Product | Paints and stains |
NAICS |
n/a
|
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $50 M to 100M |
# of Employees | 100 |
Plant Area |
100,000
ft2
|
Annual Production | 6,500,000
ton
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $105,948 | 3,934,800 |
kWh
|
$0.027 |
Electricity Demand | $77,967 | 8,364 |
kW-mo/yr
|
$9.32 |
Electricity Fees | $6,000 | - |
|
- |
Natural Gas | $156,226 | 17,198 |
MMBtu
|
$9.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,935 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $31,243 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $23,426 | $20,000 |
$(-81.0)
(-3,000)
kWh
|
$(-113.0)
-
kW-mo/yr
|
$23,620
-
MMBtu
|
- | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,719 | $800 | - | - |
$1,719
-
MMBtu
|
- | - | |
03 | 2.2163: Use minimum steam operating pressure | $2,014 | $250 | - | - |
$2,014
-
MMBtu
|
- | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,453 | $6,000 |
$3,542
131,175
kWh
|
$2,825
-
kW-mo/yr
|
$(-4,914.0)
-
MMBtu
|
- | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,002 | $1,028 |
$590
21,864
kWh
|
$412
-
kW-mo/yr
|
- | - | - | |
06 | 2.3132: Recharge batteries on during off-peak demand periods | $2,631 | - | - |
$2,631
-
kW-mo/yr
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,506 | $1,239 |
$751
27,814
kWh
|
$481
-
kW-mo/yr
|
- | - | $2,274 | |
08 | 4.212: Adopt in-house material generation | $5,184 | $9,200 |
$(-470.0)
(-17,407)
kWh
|
$(-146.0)
-
kW-mo/yr
|
- | $(-500.0) | $6,300 | |
TOTAL RECOMMENDED | $40,935 | $38,517 |
$4,332
160,446
kWh
|
$6,090
-
kW-mo/yr
|
$22,439
-
MMBtu
|
$(-500.0) | $8,574 | ||
TOTAL IMPLEMENTED | $31,243 | $27,050 |
$3,461
128,175
kWh
|
$5,343
-
kW-mo/yr
|
$22,439
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs