Assessment Year | 2000 |
---|---|
Principal Product | Door sills |
NAICS |
n/a
|
SIC | 2431: Millwork |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
350,000
ft2
|
Annual Production | 3,000,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $141,110 | 4,346,424 |
kWh
|
$0.032 |
Electricity Demand | $64,675 | 11,378 |
kW-mo/yr
|
$5.68 |
Electricity Fees | $8,168 | - |
|
- |
Natural Gas | $33,555 | 4,859 |
MMBtu
|
$6.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $42,170 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $34,848 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $1,005 | $1,000 | - | - |
$1,005
-
MMBtu
|
- | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $1,096 | $1,753 |
$395
12,309
kWh
|
$701
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.2511: Insulate bare equipment | $545 | $1,050 | - | - |
$545
-
MMBtu
|
- | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $593 | - |
$236
5,275
kWh
|
$357
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $701 | - |
$441
13,775
kWh
|
$260
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4323: Use optimum size and capacity equipment | $29,945 | $40,000 |
$6,170
192,849
kWh
|
$10,966
-
kW-mo/yr
|
$12,809
-
MMBtu
|
- | - | - | |
07 | 2.4226: Use / purchase optimum sized compressor | $1,556 | $1,000 |
$1,040
22,567
kWh
|
$516
-
kW-mo/yr
|
- | - | - | - | |
08 | 4.453: Reschedule breaks to allow for continuous production | $6,729 | $288 | - | - | - | $(-3,167.0) | $6,563 | $3,333 | |
TOTAL RECOMMENDED | $42,170 | $45,091 |
$8,282
246,775
kWh
|
$12,800
-
kW-mo/yr
|
$14,359
-
MMBtu
|
$(-3,167.0) | $6,563 | $3,333 | ||
TOTAL IMPLEMENTED | $34,848 | $44,803 |
$8,046
241,500
kWh
|
$12,443
-
kW-mo/yr
|
$14,359
-
MMBtu
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs