ITAC Assessment: DS0116
ITAC logo
ITAC Assessment: DS0116
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Commercial and Packaging Printing
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 202
Plant Area 67,000
ft2
Annual Production 72,622
lb
Production Hrs. Annual 7,488
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $126,724 3,851,407
kWh
Electricity Demand $65,651 8,676
kW-mo/yr
Electricity Fees $15,962 -
Natural Gas $4,394 696
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,041 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,230 $9,336 $2,778
84,115
kWh
$1,452
-
kW-mo/yr
- - - -
02 2.3212: Optimize plant power factor $7,178 $3,250 - - $7,178 - - -
03 2.4221: Install compressor air intakes in coolest locations $664 $600 $483
14,654
kWh
$181
-
kW-mo/yr
- - - -
04 2.2437: Recover waste heat from equipment $1,290 $662 $1,290
38,980
kWh
- - - - -
05 2.6218: Turn off equipment when not in use $464 $24 $464
14,068
kWh
- - - - -
06 3.1191: Change procedures / equipment / operating conditions $6,945 $3,518 - - - $1,703
-
lb
$(-3,052.0) $8,294
07 3.5315: Lease / purchase baler; sell cardboard to recycler $3,470 $4,750 - - - $3,470
-
lb
- -
08 3.2176: Increase use of automation $7,800 $4,900 - - - - $7,800 -
TOTAL RECOMMENDED $32,041 $27,040 $5,015
151,817
kWh
$1,633
-
kW-mo/yr
$7,178 $5,173
-
lb
$4,748 $8,294
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs