ITAC Assessment: NC0184
ITAC logo
ITAC Assessment: NC0184
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Transformers for PC's
NAICS
n/a
SIC 3677: Electronic Coils, Transformers, and Other Inductors
Sales Range $10
M
to 50
M
# of Employees 205
Plant Area 59,000
ft2
Annual Production 20,000,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,868 952,521
kWh
Electricity Demand $11,710 2,395
kW-mo/yr
Electricity Fees $3,338 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $981 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $848

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $133 $120 $99
2,052
kWh
$34
-
kW-mo/yr
- -
02 2.4224: Upgrade controls on compressors $685 $600 $294
6,155
kWh
$91
-
kW-mo/yr
- $300
03 3.5313: Increase amount of waste recovered for resale $163 $240 - - $163
-
lb
-
TOTAL RECOMMENDED $981 $960 $393
8,207
kWh
$125
-
kW-mo/yr
$163
-
lb
$300
TOTAL IMPLEMENTED $848 $840 $294
6,155
kWh
$91
-
kW-mo/yr
$163
-
lb
$300
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs