Assessment Year | 1999 |
---|---|
Principal Product | Dyed synthetic fabrics |
NAICS |
n/a
|
SIC | 2261: Finishers of Broadwoven Fabrics of Cotton |
Sales Range | $50 M to 100M |
# of Employees | 230 |
Plant Area |
140,000
ft2
|
Annual Production | 15,333,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $432,608 | 14,583,529 |
kWh
|
$0.030 |
Natural Gas | $256,348 | 62,710 |
MMBtu
|
$4.09 |
Other Energy | $479,986 | 86,459 |
MMBtu
|
$5.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $293,104 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $181,502 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Natural Gas Savings | Other Energy Savings | Water Disposal Savings | Personnel Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.5192: Modify textile dryers | $72,691 | $1,000 |
$72,691
-
MMBtu
|
- | - | - | - | |
02 | 2.8118: Check for accuracy of utility / power meters | $14,400 | $5,600 | - |
$14,400
-
MMBtu
|
- | - | - | |
03 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $15,967 | $6,000 | - |
$15,967
-
MMBtu
|
- | - | - | |
04 | 2.2223: Enhance sensitivity of temperature control and cutoff | $78,688 | $3,000 | - |
$78,688
-
MMBtu
|
- | - | - | |
05 | 2.2425: Use flue gases to heat process or service water | $10,689 | $16,800 | - |
$10,689
-
MMBtu
|
- | - | - | |
06 | 2.1133: Adjust burners for efficient operation | $6,258 | $800 |
$6,258
-
MMBtu
|
- | - | - | - | |
07 | 3.4151: Minimize water usage | $74,238 | $5,000 | - | - |
$10,238
-
Tgal
|
- | $64,000 | |
08 | 3.1191: Change procedures / equipment / operating conditions | $20,173 | $2,500 | - |
$12,493
-
MMBtu
|
$4,680
-
Tgal
|
$3,000 | - | |
TOTAL RECOMMENDED | $293,104 | $40,700 |
$78,949
-
MMBtu
|
$132,237
-
MMBtu
|
$14,918
-
Tgal
|
$3,000 | $64,000 | ||
TOTAL IMPLEMENTED | $181,502 | $14,100 |
$72,691
-
MMBtu
|
$26,893
-
MMBtu
|
$14,918
-
Tgal
|
$3,000 | $64,000 | ||
Yearly Savings* | Imp'd Cost* | Natural Gas Savings | Other Energy Savings | Water Disposal Savings | Personnel Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs