| Assessment Year | 1999 |
|---|---|
| Principal Product | Textile processing chemicals |
| NAICS |
n/a
|
| SIC | 2992: Lubricating Oils and Greases |
| Sales Range | $50 M to 100M |
| # of Employees | 162 |
| Plant Area |
150,000
ft2
|
| Annual Production | 120,000,000
lb
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $169,875 | 3,397,714 |
kWh
|
$0.050 |
| Electricity Demand | $82,921 | 10,153 |
kW-mo/yr
|
$8.17 |
| Natural Gas | $191,395 | 38,680 |
MMBtu
|
$4.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $62,015 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $61,997 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1133: Adjust burners for efficient operation | $8,380 | $700 | - | - |
$8,380
-
MMBtu
|
- | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $18 | $1,345 |
$18
293
kWh
|
- | - | - | - | |
| 03 | 2.7145: Install skylights | $4,672 | $35,090 |
$2,236
44,842
kWh
|
$2,436
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,553 | $9,000 |
$2,082
41,618
kWh
|
$1,471
-
kW-mo/yr
|
- | $1,000 | - | |
| 05 | 3.4151: Minimize water usage | $1,767 | - | - | - |
$1,159
-
MMBtu
|
- |
$608
-
Tgal
|
|
| 06 | 3.6124: Burn waste oil for heat | $40,650 | $30,000 | - | - |
$40,650
-
MMBtu
|
- | - | |
| 07 | 4.212: Adopt in-house material generation | $1,975 | $2,500 | - | - | - | - |
$1,975
-
Tgal
|
|
| TOTAL RECOMMENDED | $62,015 | $78,635 |
$4,336
86,753
kWh
|
$3,907
-
kW-mo/yr
|
$50,189
-
MMBtu
|
$1,000 |
$2,583
-
Tgal
|
||
| TOTAL IMPLEMENTED | $61,997 | $77,290 |
$4,318
86,460
kWh
|
$3,907
-
kW-mo/yr
|
$50,189
-
MMBtu
|
$1,000 |
$2,583
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs