| Assessment Year | 1997 |
|---|---|
| Principal Product | Bricks |
| NAICS |
n/a
|
| SIC | 3251: Brick and Structural Clay Tile |
| Sales Range | $5 M to 10M |
| # of Employees | 73 |
| Plant Area |
132,000
ft2
|
| Annual Production | 39,000,000
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $109,985 | 3,239,742 |
kWh
|
$0.034 |
| Electricity Demand | $78,814 | 14,182 |
kW-mo/yr
|
$5.56 |
| Electricity Fees | $1,441 | - |
|
- |
| Fuel Oil #2 | $12,000 | 1,440 |
MMBtu
|
$8.33 |
| Wood | $232,846 | 253,546 |
MMBtu
|
$0.92 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $265,377 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,930 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Wood Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $2,930 | $1,880 |
$2,647
53,634
kWh
|
$283
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 02 | 2.7135: Install occupancy sensors | $130 | $125 |
$130
4,396
kWh
|
- | - | - | - | - | - | - | |
| 03 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $1,143 | $2,915 |
$806
16,413
kWh
|
$337
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 04 | 2.2515: Use optimum thickness insulation | $2,940 | $17,640 | - | - | - |
$2,940
-
MMBtu
|
- | - | - | - | |
| 05 | 2.5194: Redesign process | $519 | $50 |
$519
10,551
kWh
|
- | - | - | - | - | - | - | |
| 06 | 3.1191: Change procedures / equipment / operating conditions | $109,730 | $100,000 | - | - |
$3,000
-
MMBtu
|
- |
$730
-
gal
|
$10,000 | $96,000 | - | |
| 07 | 3.1191: Change procedures / equipment / operating conditions | $136,000 | $100,000 | - | - |
$9,000
-
MMBtu
|
- |
$2,000
-
gal
|
$29,000 | $96,000 | - | |
| 08 | 3.1191: Change procedures / equipment / operating conditions | $11,985 | $2,850 | - | - | - |
$432
-
MMBtu
|
- | - | - | $11,553 | |
| TOTAL RECOMMENDED | $265,377 | $225,460 |
$4,102
84,994
kWh
|
$620
-
kW-mo/yr
|
$12,000
-
MMBtu
|
$3,372
-
MMBtu
|
$2,730
-
gal
|
$39,000 | $192,000 | $11,553 | ||
| TOTAL IMPLEMENTED | $2,930 | $1,880 |
$2,647
53,634
kWh
|
$283
-
kW-mo/yr
|
- | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Wood Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs