ITAC Assessment: NC0124
ITAC logo
ITAC Assessment: NC0124
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Pneumatic valves and filters
NAICS
n/a
SIC 3491: Industrial Valves
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 240,000
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $135,923 4,394,197
kWh
Electricity Demand $88,440 10,435
kW-mo/yr
Natural Gas $32,791 5,373
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $252,262 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $129,425

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings By-product Production Savings
01 2.7229: Air condition only space necessary $9,590 $3,000 $6,204
206,917
kWh
$3,386
-
kW-mo/yr
- - - - - - - - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,826 $401 $1,321
43,962
kWh
$505
-
kW-mo/yr
- - - - - - - - -
03 2.4131: Size electric motors for peak operating efficiency $5,715 $15,000 $3,732
124,560
kWh
$1,983
-
kW-mo/yr
- - - - - - - - -
04 2.7243: Improve air circulation with destratification fans / other methods $1,906 $6,030 $(-285.0)
(-9,379)
kWh
$(-200.0)
-
kW-mo/yr
$2,391
-
MMBtu
- - - - - - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $790 $270 $510
16,999
kWh
$280
-
kW-mo/yr
- - - - - - - - -
06 2.2625: Chill water to the highest temperature possible $245 $10 $130
4,396
kWh
$115
-
kW-mo/yr
- - - - - - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,913 $6,240 $317
10,551
kWh
$176
-
kW-mo/yr
- - - - - - $1,420 - -
08 2.7111: Reduce illumination to minimum necessary levels $2,572 $2,000 $1,402
46,600
kWh
$1,170
-
kW-mo/yr
- - - - - - - - -
09 3.4151: Minimize water usage $2,770 $5,910 $(-168.0)
(-5,569)
kWh
$(-93.0)
-
kW-mo/yr
- $3,031
-
Tgal
- - - - - - -
10 3.7393: Implement a machine and coolant sump cleaning program to minimize coolant contamination $7,405 - - - - - $8,210
-
gal
- - $(-605.0) $(-200.0) - -
11 3.3132: Use reverse osmosis to concentrate material $2,755 $2,830 $(-105.0)
(-3,517)
kWh
$(-40.0)
-
kW-mo/yr
- - - - $3,200
-
lb
$(-300.0) - - -
12 3.5316: Contract a wood pallet recycling company $375 $200 - - - - - $375
-
lb
- - - - -
13 4.521: Clear and rent existing space $110,000 $15,000 - - - - - - - - - - $110,000
14 4.611: Begin a practice of predictive / preventative maintenance $12,000 $8,500 - - - - - - - - $5,000 $7,000 -
15 4.442: Install magazines for temporary storage $92,400 $35,000 - - - - - - - $92,400 - - -
TOTAL RECOMMENDED $252,262 $100,391 $13,058
435,520
kWh
$7,282
-
kW-mo/yr
$2,391
-
MMBtu
$3,031
-
Tgal
$8,210
-
gal
$375
-
lb
$3,200
-
lb
$91,495 $6,220 $7,000 $110,000
TOTAL IMPLEMENTED $129,425 $57,840 $8,328
277,550
kWh
$4,972
-
kW-mo/yr
- - $8,210
-
gal
- $3,200
-
lb
$91,495 $6,220 $7,000 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs