Assessment Year | 1997 |
---|---|
Principal Product | Cases for electronics |
NAICS |
n/a
|
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 135 |
Plant Area |
130,000
ft2
|
Annual Production | 13,000
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $61,824 | 1,546,014 |
kWh
|
$0.040 |
Electricity Demand | $38,097 | 4,646 |
kW-mo/yr
|
$8.20 |
LPG | $16,571 | 1,397 |
MMBtu
|
$11.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $157,232 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $128,137 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $1,987 | - |
$1,987
49,824
kWh
|
- | - | - | - | - | - | - | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $953 | $450 |
$590
14,654
kWh
|
$363
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.7131: Add area lighting switches | $1,475 | $2,000 |
$1,475
36,928
kWh
|
- | - | - | - | - | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $126 | $25 |
$78
2,052
kWh
|
$48
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
05 | 2.4224: Upgrade controls on compressors | $376 | $400 |
$256
6,448
kWh
|
$120
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
06 | 2.7243: Improve air circulation with destratification fans / other methods | $7,282 | $14,319 |
$(-946.0)
(-23,740)
kWh
|
$(-465.0)
-
kW-mo/yr
|
$8,693
-
MMBtu
|
- | - | - | - | - | - | |
07 | 3.1222: Reduce water use with counter current rinsing | $926 | $200 | - | - | - |
$926
-
Tgal
|
- | - | - | - | - | |
08 | 3.3125: Use distillation, evaporation to remove contaminants | $14,528 | $12,000 |
$(-256.0)
(-6,448)
kWh
|
- | - | - |
$14,784
-
gal
|
- | - | - | - | |
09 | 3.1192: Reduce scrap production | $3,429 | $15,000 | - | - | - | - | - | - | - | $3,429 | - | |
10 | 3.5316: Contract a wood pallet recycling company | $375 | $200 | - | - | - | - | - |
$375
-
lb
|
- | - | - | |
11 | 4.515: Install shelves / racks to utilize unused space | $10,775 | - | - | - | - | - | - | - | $10,775 | - | - | |
12 | 4.424: Improve space comfort conditioning | $115,000 | $200,000 | - | - | - | - | - | - | - | - | $115,000 | |
TOTAL RECOMMENDED | $157,232 | $244,594 |
$3,184
79,718
kWh
|
$66
-
kW-mo/yr
|
$8,693
-
MMBtu
|
$926
-
Tgal
|
$14,784
-
gal
|
$375
-
lb
|
$10,775 | $3,429 | $115,000 | ||
TOTAL IMPLEMENTED | $128,137 | $200,200 |
$1,987
49,824
kWh
|
- | - | - | - |
$375
-
lb
|
$10,775 | - | $115,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs