ITAC Assessment: NC0118
ITAC logo
ITAC Assessment: NC0118
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product electro-pneumatic controls
NAICS
n/a
SIC 3743: Railroad Equipment
Sales Range $10
M
to 50
M
# of Employees 275
Plant Area 437,000
ft2
Annual Production 5,600,000
lb
Production Hrs. Annual 4,000
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $177,716 10,531,360
kWh
Electricity Demand $203,705 22,484
kW-mo/yr
Electricity Fees $57,357 -
Natural Gas $112,412 26,818
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,002,670 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,428

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Ancillary Material Cost Savings Primary Product Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,752 $690 $671
39,859
kWh
$1,081
-
kW-mo/yr
- - - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $803 $249 $307
18,171
kWh
$496
-
kW-mo/yr
- - - -
03 2.4239: Eliminate or reduce compressed air usage $1,932 $2,000 $758
44,842
kWh
$1,174
-
kW-mo/yr
- - - -
04 2.7314: Reduce ventilation air $3,671 $12,046 - - $3,671
-
MMBtu
- - -
05 2.4226: Use / purchase optimum sized compressor $27,676 - $1,107
65,651
kWh
$3,569
-
kW-mo/yr
- - $23,000 -
06 2.4239: Eliminate or reduce compressed air usage $1,960 $606 $465
27,550
kWh
$1,495
-
kW-mo/yr
- - - -
07 3.2123: Convert to high volume low pressure (hvlp) paint guns $680 $500 - - - $680
-
gal
- -
08 3.3128: Utilize other methods to remove contaminants $8,290 - $300
17,878
kWh
$190
-
kW-mo/yr
- - $7,800 -
09 4.112: Replace old machine with new automatic multi-station tool $942,500 $1,200,000 - - - - - $942,500
10 4.651: Install back-up equipment $13,406 $21,000 - - - - $13,406 -
TOTAL RECOMMENDED $1,002,670 $1,237,091 $3,608
213,951
kWh
$8,005
-
kW-mo/yr
$3,671
-
MMBtu
$680
-
gal
$44,206 $942,500
TOTAL IMPLEMENTED $29,428 $690 $1,778
105,510
kWh
$4,650
-
kW-mo/yr
- - $23,000 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs