Assessment Year | 2002 |
---|---|
Principal Product | Investment Castings |
NAICS |
n/a
|
SIC | 3324: Steel Investment Foundries |
Sales Range | $5 M to 10M |
# of Employees | 80 |
Plant Area |
41,000
ft2
|
Annual Production | 830
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $211,137 | 4,915,101 |
kWh
|
$0.043 |
Electricity Demand | $159,349 | 16,815 |
kW-mo/yr
|
$9.48 |
Natural Gas | $247,708 | 32,962 |
MMBtu
|
$7.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,661 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,000 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $15,624 | - | - |
$15,624
-
kW-mo/yr
|
- | |
02 | 2.3191: Use demand controller or load shedder | $11,376 | $4,500 | - |
$11,376
-
kW-mo/yr
|
- | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,486 | $500 | - | - |
$1,486
-
MMBtu
|
|
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $238 | - |
$238
7,761
kWh
|
- | - | |
05 | 2.2437: Recover waste heat from equipment | $2,937 | $6,200 | - | - |
$2,937
-
MMBtu
|
|
TOTAL RECOMMENDED | $31,661 | $11,200 |
$238
7,761
kWh
|
$27,000
-
kW-mo/yr
|
$4,423
-
MMBtu
|
||
TOTAL IMPLEMENTED | $27,000 | $4,500 | - |
$27,000
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs