Assessment Year | 1996 |
---|---|
Principal Product | Yarn |
NAICS |
n/a
|
SIC | 2281: Yarn Spinning Mills |
Sales Range | $10 M to 50M |
# of Employees | 260 |
Plant Area |
109,375
ft2
|
Annual Production | 9,500,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $778,267 | 20,672,333 |
kWh
|
$0.038 |
Electricity Demand | $510,363 | 35,280 |
kW-mo/yr
|
$14.47 |
Electricity Fees | $38,659 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,769 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,919 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $13,500 | $6,167 |
$8,852
235,346
kWh
|
$4,648
-
kW-mo/yr
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,267 | $2,925 |
$1,267
33,705
kWh
|
- | - | |
03 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $3,391 | $5,000 |
$2,134
56,565
kWh
|
$1,257
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,152 | $350 |
$755
19,930
kWh
|
$397
-
kW-mo/yr
|
- | |
05 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $3,167 | $530 |
$2,037
54,220
kWh
|
$1,130
-
kW-mo/yr
|
- | |
06 | 2.4239: Eliminate or reduce compressed air usage | $8,100 | $10,000 |
$5,309
140,973
kWh
|
$2,791
-
kW-mo/yr
|
- | |
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $192 | $100 | - | - |
$192
-
lb
|
|
TOTAL RECOMMENDED | $30,769 | $25,072 |
$20,354
540,739
kWh
|
$10,223
-
kW-mo/yr
|
$192
-
lb
|
||
TOTAL IMPLEMENTED | $25,919 | $17,047 |
$16,953
450,469
kWh
|
$8,966
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs