ITAC Assessment: NC0083
ITAC logo
ITAC Assessment: NC0083
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Pickled Cucumbers
NAICS
n/a
SIC 2035: Pickled Fruits and Vegetables, Vegetable Sauces and Seasonings, and Salad Dressings
Sales Range $50
M
to 100
M
# of Employees 250
Plant Area 200,000
ft2
Annual Production 7,500,000
units
Production Hrs. Annual 5,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $261,443 7,924,678
kWh
Electricity Demand $141,690 16,761
kW-mo/yr
Fuel Oil #6 $179,894 56,414
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $70,201 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,289

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #6 Savings Water Disposal Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,850 $1,578 $1,091
33,118
kWh
$759
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $108 $560 $50
1,465
kWh
$18
-
kW-mo/yr
- - $40
03 2.7134: Use photocell controls $2,242 $660 $1,014
30,774
kWh
$1,228
-
kW-mo/yr
- - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $859 $30 $535
16,120
kWh
$324
-
kW-mo/yr
- - -
05 2.7447: Install vinyl strip / high speed / air curtain doors $605 $600 $162
4,982
kWh
$443
-
kW-mo/yr
- - -
06 2.4133: Use most efficient type of electric motors $2,187 $3,224 $1,640
49,824
kWh
$547
-
kW-mo/yr
- - -
07 2.1233: Analyze flue gas for proper air/fuel ratio $1,902 $600 - - $1,902
-
MMBtu
- -
08 3.4111: Use closed cycle process to minimize waste water production $1,683 $2,500 $(-205.0)
(-6,155)
kWh
$(-250.0)
-
kW-mo/yr
- $2,138
-
Tgal
-
09 3.4114: Replace city water with recycled water via cooling tower $58,765 $10,360 $(-1,034.0)
(-31,360)
kWh
$(-393.0)
-
kW-mo/yr
- $60,192
-
Tgal
-
TOTAL RECOMMENDED $70,201 $20,112 $3,253
98,768
kWh
$2,676
-
kW-mo/yr
$1,902
-
MMBtu
$62,330
-
Tgal
$40
TOTAL IMPLEMENTED $8,289 $6,622 $3,795
115,181
kWh
$2,552
-
kW-mo/yr
$1,902
-
MMBtu
- $40
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #6 Savings Water Disposal Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs