Assessment Year | 1996 |
---|---|
Principal Product | Fabricated metal parts |
NAICS |
n/a
|
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 62 |
Plant Area |
47,225
ft2
|
Annual Production | 10,000,000
lb
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $39,950 | 822,685 |
kWh
|
$0.049 |
Electricity Demand | $25,050 | 3,000 |
kW-mo/yr
|
$8.35 |
Natural Gas | $8,496 | 1,717 |
MMBtu
|
$4.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,054 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,053 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,351 | $2,860 |
$579
17,292
kWh
|
$772
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $132 | $840 |
$98
2,931
kWh
|
$34
-
kW-mo/yr
|
- | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $278 | $210 |
$185
5,569
kWh
|
$93
-
kW-mo/yr
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $544 | $160 |
$317
9,672
kWh
|
$227
-
kW-mo/yr
|
- | - | |
05 | 2.4226: Use / purchase optimum sized compressor | $775 | - |
$775
28,429
kWh
|
- | - | - | |
06 | 2.2511: Insulate bare equipment | $306 | $100 |
$188
7,034
kWh
|
$118
-
kW-mo/yr
|
- | - | |
07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,818 | $5,000 |
$2,849
72,392
kWh
|
$3,637
-
kW-mo/yr
|
$(-1,668.0)
-
MMBtu
|
- | |
08 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $9,850 | $1,800 | - | - | - |
$9,850
-
lb
|
|
TOTAL RECOMMENDED | $18,054 | $10,970 |
$4,991
143,319
kWh
|
$4,881
-
kW-mo/yr
|
$(-1,668.0)
-
MMBtu
|
$9,850
-
lb
|
||
TOTAL IMPLEMENTED | $1,053 | $210 |
$960
33,998
kWh
|
$93
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs