| Assessment Year | 1995 |
|---|---|
| Principal Product | Pantyhose |
| NAICS |
n/a
|
| SIC | 2251: Women's Full-Length and Knee-Length Hosiery, Except Socks |
| Sales Range | $50 M to 100M |
| # of Employees | 365 |
| Plant Area |
130,000
ft2
|
| Annual Production | 54,000,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $423,351 | 11,228,019 |
kWh
|
$0.038 |
| Fuel Oil #2 | $62,314 | 20,438 |
MMBtu
|
$3.05 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $21,115 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,141 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $1,626 | - |
$1,626
43,083
kWh
|
- | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $7,215 | $19,196 |
$7,215
191,383
kWh
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $354 | $2,430 |
$354
8,206
kWh
|
- | |
| 04 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $4,567 | $15,000 |
$4,567
121,043
kWh
|
- | |
| 05 | 2.7241: Install outside air damper / economizer on hvac unit | $2,838 | $15,000 |
$2,838
75,322
kWh
|
- | |
| 06 | 2.2136: Install / repair insulation on steam lines | $2,634 | $4,545 | - |
$2,634
-
MMBtu
|
|
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $463 | $1,556 |
$463
12,309
kWh
|
- | |
| 08 | 2.7111: Reduce illumination to minimum necessary levels | $1,418 | $1,500 |
$1,418
37,515
kWh
|
- | |
| TOTAL RECOMMENDED | $21,115 | $59,227 |
$18,481
488,861
kWh
|
$2,634
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $6,141 | $7,601 |
$3,507
92,907
kWh
|
$2,634
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs