| Assessment Year | 1995 |
|---|---|
| Principal Product | Cotton Yarn |
| NAICS |
n/a
|
| SIC | 2281: Yarn Spinning Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 121 |
| Plant Area |
226,000
ft2
|
| Annual Production | 26,500,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,454,736 | 29,864,596 |
kWh
|
$0.049 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $186,682 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $58,204 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,340 | - |
$3,340
68,288
kWh
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $802 | $450 |
$802
16,413
kWh
|
- | - | |
| 03 | 2.3113: Make ice during off peak hours for cooling | $95,329 | $560,000 |
$95,329
1,331,477
kWh
|
- | - | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $14,062 | $1,540 |
$14,062
230,657
kWh
|
- | - | |
| 05 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $6,149 | $7,500 |
$6,149
229,484
kWh
|
- | - | |
| 06 | 3.4115: Recover and reuse cooling water | $27,000 | $6,000 | - |
$27,000
-
Tgal
|
- | |
| 07 | 3.5311: Recover and reuse waste material | $40,000 | - | - | - |
$40,000
-
lb
|
|
| TOTAL RECOMMENDED | $186,682 | $575,490 |
$119,682
1,876,319
kWh
|
$27,000
-
Tgal
|
$40,000
-
lb
|
||
| TOTAL IMPLEMENTED | $58,204 | $1,990 |
$18,204
315,358
kWh
|
- |
$40,000
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs