Assessment Year | 1995 |
---|---|
Principal Product | Precision Metering Pumps |
NAICS |
n/a
|
SIC | 3561: Pumps and Pumping Equipment |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
52,000
ft2
|
Annual Production | 6,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $195,817 | 3,666,178 |
kWh
|
$0.053 |
Natural Gas | $413 | 62 |
MMBtu
|
$6.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,849 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,681 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $168 | $152 |
$168
3,224
kWh
|
- | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $2,092 | $250 |
$2,092
39,566
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,032 | $480 |
$3,032
57,151
kWh
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,969 | $620 |
$3,969
75,029
kWh
|
- | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $1,813 | $320 |
$1,813
32,532
kWh
|
- | - | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $2,221 | - |
$2,221
81,477
kWh
|
- | - | |
07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,168 | $4,000 |
$2,582
19,343
kWh
|
$(-414.0)
-
MMBtu
|
- | |
08 | 3.5316: Contract a wood pallet recycling company | $200 | $100 | - | - |
$200
-
lb
|
|
09 | 3.5313: Increase amount of waste recovered for resale | $186 | $100 | - | - |
$186
-
lb
|
|
TOTAL RECOMMENDED | $15,849 | $6,022 |
$15,877
308,322
kWh
|
$(-414.0)
-
MMBtu
|
$386
-
lb
|
||
TOTAL IMPLEMENTED | $13,681 | $2,022 |
$13,295
288,979
kWh
|
- |
$386
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs