Assessment Year | 1995 |
---|---|
Principal Product | Pickled cucumbers and peppers |
NAICS |
n/a
|
SIC | 2035: Pickled Fruits and Vegetables, Vegetable Sauces and Seasonings, and Salad Dressings |
Sales Range | $100 M to 500M |
# of Employees | 350 |
Plant Area |
100,000
ft2
|
Annual Production | 40,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $459,755 | 7,971,864 |
kWh
|
$0.058 |
Fuel Oil #2 | $159,752 | 61,016 |
MMBtu
|
$2.62 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $104,186 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,728 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,358 | $2,000 |
$1,358
29,894
kWh
|
- | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $403 | $100 |
$403
7,327
kWh
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,087 | $120 |
$1,087
22,860
kWh
|
- | - | - | - | |
04 | 2.7241: Install outside air damper / economizer on hvac unit | $6,703 | $15,000 |
$6,703
214,537
kWh
|
- | - | - | - | |
05 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $784 | $900 | - |
$784
-
MMBtu
|
- | - | - | |
06 | 2.1232: Keep boiler tubes clean | $8,880 | - | - |
$8,880
-
MMBtu
|
- | - | - | |
07 | 3.6192: Use a less expensive method of waste removal | $1,850 | - | - | - | - | - |
$1,850
-
lb
|
|
08 | 3.1191: Change procedures / equipment / operating conditions | $71,177 | $500 | - | - | - |
$71,177
-
gal
|
- | |
09 | 3.4111: Use closed cycle process to minimize waste water production | $11,944 | $18,477 | - | - |
$11,944
-
Tgal
|
- | - | |
TOTAL RECOMMENDED | $104,186 | $37,097 |
$9,551
274,618
kWh
|
$9,664
-
MMBtu
|
$11,944
-
Tgal
|
$71,177
-
gal
|
$1,850
-
lb
|
||
TOTAL IMPLEMENTED | $11,728 | $2,220 |
$2,848
60,081
kWh
|
$8,880
-
MMBtu
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs