ITAC Assessment: NC0052
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Pickled cucumbers and peppers
NAICS
n/a
SIC 2035: Pickled Fruits and Vegetables, Vegetable Sauces and Seasonings, and Salad Dressings
Sales Range $100
M
to 500
M
# of Employees 350
Plant Area 100,000
ft2
Annual Production 40,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $459,755 7,971,864
kWh
Fuel Oil #2 $159,752 61,016
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $104,186 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,728

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,358 $2,000 $1,358
29,894
kWh
- - - -
02 2.4221: Install compressor air intakes in coolest locations $403 $100 $403
7,327
kWh
- - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,087 $120 $1,087
22,860
kWh
- - - -
04 2.7241: Install outside air damper / economizer on hvac unit $6,703 $15,000 $6,703
214,537
kWh
- - - -
05 2.1243: Use heat from boiler blowdown to preheat boiler feed water $784 $900 - $784
-
MMBtu
- - -
06 2.1232: Keep boiler tubes clean $8,880 - - $8,880
-
MMBtu
- - -
07 3.6192: Use a less expensive method of waste removal $1,850 - - - - - $1,850
-
lb
08 3.1191: Change procedures / equipment / operating conditions $71,177 $500 - - - $71,177
-
gal
-
09 3.4111: Use closed cycle process to minimize waste water production $11,944 $18,477 - - $11,944
-
Tgal
- -
TOTAL RECOMMENDED $104,186 $37,097 $9,551
274,618
kWh
$9,664
-
MMBtu
$11,944
-
Tgal
$71,177
-
gal
$1,850
-
lb
TOTAL IMPLEMENTED $11,728 $2,220 $2,848
60,081
kWh
$8,880
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #2 Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs