Assessment Year | 1994 |
---|---|
Principal Product | Conveyors & Motorized Pulleys |
NAICS |
n/a
|
SIC | 3562: Ball and Roller Bearings |
Sales Range | $10 M to 50M |
# of Employees | 220 |
Plant Area |
245,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $186,817 | 3,345,252 |
kWh
|
$0.056 |
LPG | $12,989 | 2,072 |
MMBtu
|
$6.27 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,867 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,189 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $659 | $480 |
$659
11,723
kWh
|
- | |
02 | 2.4239: Eliminate or reduce compressed air usage | $1,912 | $1,600 |
$1,912
34,291
kWh
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $723 | $360 |
$723
12,896
kWh
|
- | |
04 | 2.2437: Recover waste heat from equipment | $2,044 | $3,000 | - |
$2,044
-
MMBtu
|
|
05 | 2.2628: Utilize a less expensive cooling method | $10,722 | - |
$10,722
192,556
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $807 | $1,190 |
$807
14,361
kWh
|
- | |
TOTAL RECOMMENDED | $16,867 | $6,630 |
$14,823
265,827
kWh
|
$2,044
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,189 | $2,030 |
$2,189
38,980
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs