| Assessment Year | 1994 |
|---|---|
| Principal Product | Dry packages soups and sauces |
| NAICS |
n/a
|
| SIC | 2034: Dried and Dehydrated Fruits, Vegetables, and Soup Mixes |
| Sales Range | $10 M to 50M |
| # of Employees | 113 |
| Plant Area |
141,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $275,116 | 5,539,273 |
kWh
|
$0.050 |
| Natural Gas | $99,709 | 24,766 |
MMBtu
|
$4.03 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $349,067 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $385 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3132: Recharge batteries on during off-peak demand periods | $1,130 | - |
$1,130
-
kWh
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $385 | $770 |
$385
7,620
kWh
|
- | |
| 03 | 2.7241: Install outside air damper / economizer on hvac unit | $3,610 | $7,500 |
$3,610
134,818
kWh
|
- | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $122,824 | $35,000 |
$86,051
1,732,122
kWh
|
$36,773
-
MMBtu
|
|
| 05 | 2.2437: Recover waste heat from equipment | $72,336 | $30,000 |
$14,003
281,946
kWh
|
$58,333
-
MMBtu
|
|
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $148,485 | $65,000 |
$90,152
1,814,478
kWh
|
$58,333
-
MMBtu
|
|
| 07 | 2.2136: Install / repair insulation on steam lines | $297 | $97 | - |
$297
-
MMBtu
|
|
| TOTAL RECOMMENDED | $349,067 | $138,367 |
$195,331
3,970,984
kWh
|
$153,736
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $385 | $770 |
$385
7,620
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs