| Assessment Year | 2024 |
|---|---|
| Principal Product | chimney caps |
| NAICS | 332322: Sheet Metal Work Manufacturing |
| SIC | 3444: Sheet Metal Work |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
122,300
ft2
|
| Annual Production | 478,000
pieces
|
| Production Hrs. Annual | 2,125
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $49,439 | 535,689 |
kWh
|
$0.092 | |
| Electricity Demand | $16,698 | 3,976 |
kW-mo/yr
|
$4.20 | |
| Natural Gas | $138,730 | 14,516 |
MMBtu
|
$9.56 | |
| Waste Disposal Costs | |||||
| Water Usage | $15,178 | 1,834 |
Tgal
|
$8.28 | |
| TOTAL YEARLY COSTS | $220,045 | ||||
| RECOMMENDED SAVINGS* | $21,856 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $7,978 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $1,834 | $5,300 |
$448
4,896
kWh
|
$1,386
-
kW-mo/yr
|
- | |
| 02 | 2.4235: Remove or close off unneeded compressed air lines | $8,851 | $11,852 |
$8,851
96,209
kWh
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,978 | $18,853 |
$7,978
86,713
kWh
|
- | - | |
| 04 | 2.2437: Recover waste heat from equipment | $3,193 | $8,300 | - | - |
$3,193
-
MMBtu
|
|
| TOTAL RECOMMENDED | $21,856 | $44,305 |
$17,277
187,818
kWh
|
$1,386
-
kW-mo/yr
|
$3,193
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $7,978 | $18,853 |
$7,978
86,713
kWh
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs