| Assessment Year | 2022 |
|---|---|
| Principal Product | domestic and industrial wastewater |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | less than $500 k |
| # of Employees | 12 |
| Plant Area |
100,176
ft2
|
| Annual Production | 5,292,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $398,122 | 7,596,000 |
kWh
|
$0.052 | |
| Electricity Demand | $39,952 | 14,612 |
kW-mo/yr
|
$2.73 | |
| Natural Gas | $73,412 | 12,177 |
MMBtu
|
$6.03 | |
| Waste Disposal Costs | |||||
| Water Usage | $64,448 | 10,699 |
Tgal
|
$6.02 | |
| TOTAL YEARLY COSTS | $575,934 | ||||
| RECOMMENDED SAVINGS* | $444,467 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $163,563 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.6231: Utilize controls to operate equipment only when needed | $113,192 | - |
$113,192
2,177,000
kWh
|
- | - | - | |
| 02 | 2.9114: Use solar heat to make electricty | $56,407 | $636,000 |
$56,407
1,084,750
kWh
|
- | - | - | |
| 03 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $224,497 | $226,000 |
$(-4,338.0)
(-83,432)
kWh
|
$(-368.0)
-
kW-mo/yr
|
- | $229,203 | |
| 04 | 3.4151: Minimize water usage | $50,371 | $4,080 |
$(-142.0)
(-2,728)
kWh
|
$(-25.0)
-
kW-mo/yr
|
$50,538
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $444,467 | $866,080 |
$165,119
3,175,590
kWh
|
$(-393.0)
-
kW-mo/yr
|
$50,538
-
Tgal
|
$229,203 | ||
| TOTAL IMPLEMENTED | $163,563 | $4,080 |
$113,050
2,174,272
kWh
|
$(-25.0)
-
kW-mo/yr
|
$50,538
-
Tgal
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs