Assessment Year | 2022 |
---|---|
Principal Product | Auto door panels, Consoles |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $100 M to 500M |
# of Employees | 489 |
Plant Area |
332,000
ft2
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 5,760
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $507,438 | 6,458,949 |
kWh
|
$0.079 | |
Electricity Demand | $167,516 | 39,276 |
kW-mo/yr
|
$4.27 | |
Natural Gas | $141,792 | 7,465 |
MMBtu
|
$18.99 | |
Waste Disposal Costs | |||||
Water Usage | $6,842 | 1,095 |
Tgal
|
$6.25 | |
TOTAL YEARLY COSTS | $823,588 | ||||
RECOMMENDED SAVINGS* | $95,049 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $18,857 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $1,260 | $480 |
$1,155
14,623
kWh
|
$105
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $5,050 | $7,800 |
$4,539
57,451
kWh
|
$511
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $269 | $340 |
$269
3,406
kWh
|
- | - | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $12,278 | $240 | - | - |
$12,278
-
MMBtu
|
|
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,182 | $17,137 |
$10,411
131,783
kWh
|
$771
-
kW-mo/yr
|
- | |
06 | 2.9114: Use solar heat to make electricty | $65,010 | $664,200 |
$60,506
765,904
kWh
|
$4,504
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $95,049 | $690,197 |
$76,880
973,167
kWh
|
$5,891
-
kW-mo/yr
|
$12,278
-
MMBtu
|
||
TOTAL IMPLEMENTED | $18,857 | $8,860 |
$5,963
75,480
kWh
|
$616
-
kW-mo/yr
|
$12,278
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs