Assessment Year | 2000 |
---|---|
Principal Product | Metal storage Buildings |
NAICS |
n/a
|
SIC | 3448: Prefabricated Metal Buildings and Components |
Sales Range | $50 M to 100M |
# of Employees | 270 |
Plant Area |
300,000
ft2
|
Annual Production | 450,000
units
|
Production Hrs. Annual | 4,320
hrs
|
Location (State) | not found |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $226,140 | 3,521,395 |
kWh
|
$0.064 |
Electricity Fees | $11,089 | - |
|
- |
Natural Gas | $65,693 | 15,550 |
MMBtu
|
$4.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,501 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,118 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,555 | $13,420 |
$7,555
117,819
kWh
|
- | - | - | - | - | |
02 | 2.7135: Install occupancy sensors | $3,918 | $930 |
$3,918
60,961
kWh
|
- | - | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $3,648 | $1,125 |
$3,648
53,634
kWh
|
- | - | - | - | - | |
04 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $826 | - |
$826
12,896
kWh
|
- | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $245 | $235 |
$149
2,345
kWh
|
- | - | - | $56 | $40 | |
06 | 3.6114: Use precipitating agents in waste water treatment that produce the least quantity of waste | $1,494 | $4,825 | - |
$1,494
-
Tgal
|
- | - | - | - | |
07 | 3.7211: Modify material application methods | $1,171 | $1,500 | - | - |
$1,171
-
gal
|
- | - | - | |
08 | 4.447: Automate payroll system | $7,644 | $7,000 | - | - | - | $7,644 | - | - | |
TOTAL RECOMMENDED | $26,501 | $29,035 |
$16,096
247,655
kWh
|
$1,494
-
Tgal
|
$1,171
-
gal
|
$7,644 | $56 | $40 | ||
TOTAL IMPLEMENTED | $17,118 | $16,975 |
$15,947
245,310
kWh
|
- |
$1,171
-
gal
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs