| Assessment Year | 2022 |
|---|---|
| Principal Product | Air filtration products |
| NAICS | 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
| SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
175,000
ft2
|
| Annual Production | 1,000,000
pieces
|
| Production Hrs. Annual | 4,320
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $284,615 | 2,292,800 |
kWh
|
$0.12 | |
| Natural Gas | $39,229 | 590 |
MMBtu
|
$66.49 | |
| Waste Disposal Costs | |||||
| Water Usage | $4,352 | 421 |
Tgal
|
$10.33 | |
| TOTAL YEARLY COSTS | $328,196 | ||||
| RECOMMENDED SAVINGS* | $216,808 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $27,975 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7231: Use radiant heater for spot heating | $15,635 | $15,360 |
$(-1,607.0)
(-12,960)
kWh
|
$17,242
-
MMBtu
|
- | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $2,404 | $480 |
$2,404
19,385
kWh
|
- | - | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $2,771 | $14,420 |
$2,771
22,350
kWh
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,247 | $250 |
$2,247
18,128
kWh
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $3,818 | $360 |
$3,818
30,793
kWh
|
- | - | |
| 06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $16,735 | $15,782 |
$(-326.0)
(-2,629)
kWh
|
$17,061
-
MMBtu
|
- | |
| 07 | 2.8114: Change rate schedules or other changes in utility service | $34,981 | $1,350 | - | - | $34,981 | |
| 08 | 2.9114: Use solar heat to make electricty | $138,217 | $836,000 |
$138,217
1,114,652
kWh
|
- | - | |
| TOTAL RECOMMENDED | $216,808 | $884,002 |
$147,524
1,189,719
kWh
|
$34,303
-
MMBtu
|
$34,981 | ||
| TOTAL IMPLEMENTED | $27,975 | $31,292 |
$10,914
88,027
kWh
|
$17,061
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs