Assessment Year | 2021 |
---|---|
Principal Product | Bullets and Amunitions |
NAICS | 332992: Small Arms Ammunition Manufacturing |
SIC | 3482: Small Arms Ammunition |
Sales Range | $10 M to 50M |
# of Employees | 140 |
Plant Area |
44,000
ft2
|
Annual Production | 200,000,000
units
|
Production Hrs. Annual | 5,900
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $36,087 | 989,679 |
kWh
|
$0.036 | |
Electricity Demand | $54,605 | 3,560 |
kW-mo/yr
|
$15.34 | |
Electricity Fees | $8,037 | - |
|
- | |
Natural Gas | $9,356 | 1,354 |
MMBtu
|
$6.91 | |
Waste Disposal Costs | |||||
Water Disposal | $14,000 | 10 |
Tgal
|
$1,400.00 | |
TOTAL YEARLY COSTS | $122,085 | ||||
RECOMMENDED SAVINGS* | $34,094 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $26,453 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.3128: Utilize other methods to remove contaminants | $26,453 | $92,586 | - | - | - | $26,453 | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,459 | $2,700 |
$1,560
42,749
kWh
|
$898
-
kW-mo/yr
|
- | - | |
03 | 2.3212: Optimize plant power factor | $2,375 | $6,744 | - | - | - | $2,375 | |
04 | 2.6218: Turn off equipment when not in use | $1,530 | $500 |
$1,530
41,928
kWh
|
- | - | - | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $731 | $2,000 |
$380
10,432
kWh
|
- |
$351
-
MMBtu
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $546 | $550 |
$321
8,788
kWh
|
$225
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $34,094 | $105,080 |
$3,791
103,896
kWh
|
$1,123
-
kW-mo/yr
|
$351
-
MMBtu
|
$28,828 | ||
TOTAL IMPLEMENTED | $26,453 | $92,586 | - | - | - | $26,453 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs