Assessment Year | 2020 |
---|---|
Principal Product | Plastic Packaging |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 75 |
Plant Area |
61,425
ft2
|
Annual Production | 200,000
lb
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $476,362 | 6,835,959 |
kWh
|
$0.070 | |
Electricity Demand | $55,038 | 15,696 |
kW-mo/yr
|
$3.51 | |
Electricity Fees | $2,545 | - |
|
- | |
Natural Gas | $11,628 | 1,433 |
MMBtu
|
$8.11 | |
Waste Disposal Costs | |||||
Water Usage | $33,499 | 7,356 |
Tgal
|
$4.55 | |
TOTAL YEARLY COSTS | $579,072 | ||||
RECOMMENDED SAVINGS* | $12,683 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $10,065 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4224: Upgrade controls on compressors | $4,714 | $3,096 |
$4,223
60,584
kWh
|
$491
-
kW-mo/yr
|
- | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,851 | $3,250 | - |
$1,851
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,559 | $1,091 |
$1,611
23,120
kWh
|
$187
-
kW-mo/yr
|
$(-240.0) | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,247 | $2,264 |
$1,117
16,024
kWh
|
$130
-
kW-mo/yr
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,411 | $298 |
$1,264
18,129
kWh
|
$147
-
kW-mo/yr
|
- | |
06 | 2.7135: Install occupancy sensors | $1,134 | $4,935 |
$1,016
14,579
kWh
|
$118
-
kW-mo/yr
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $767 | $1,272 |
$630
9,040
kWh
|
$137
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $12,683 | $16,206 |
$9,861
141,476
kWh
|
$3,061
-
kW-mo/yr
|
$(-240.0) | ||
TOTAL IMPLEMENTED | $10,065 | $11,684 |
$9,231
132,436
kWh
|
$1,073
-
kW-mo/yr
|
$(-240.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs