Assessment Year | 2019 |
---|---|
Principal Product | Assemble machines with fixtures and tooling for automated welding applic |
NAICS | 333249: Other Industrial Machinery Manufacturing |
SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 128 |
Plant Area |
128,575
ft2
|
Annual Production | 772
units
|
Production Hrs. Annual | 3,636
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $93,872 | 1,087,200 |
kWh
|
$0.086 |
Electricity Demand | $13,716 | 4,077 |
kW-mo/yr
|
$3.36 |
Natural Gas | $15,180 | 2,065 |
MMBtu
|
$7.35 |
TOTAL YEARLY COSTS | $122,767 | |||
RECOMMENDED SAVINGS* | $47,673 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $47,673 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $155 | $60 |
$137
1,592
kWh
|
$18
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $249 | $1,040 |
$221
2,577
kWh
|
$28
-
kW-mo/yr
|
- | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $2,641 | $180 |
$2,271
26,408
kWh
|
$370
-
kW-mo/yr
|
- | |
04 | 2.2622: Replace existing chiller with high efficiency model | $44,070 | $184,040 |
$35,734
316,224
kWh
|
$2,333
-
kW-mo/yr
|
$6,003
-
MMBtu
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $367 | $120 |
$367
4,270
kWh
|
- | - | |
06 | 2.7135: Install occupancy sensors | $191 | $390 |
$191
2,225
kWh
|
- | - | |
TOTAL RECOMMENDED | $47,673 | $185,830 |
$38,921
353,296
kWh
|
$2,749
-
kW-mo/yr
|
$6,003
-
MMBtu
|
||
TOTAL IMPLEMENTED | $47,673 | $185,830 |
$38,921
353,296
kWh
|
$2,749
-
kW-mo/yr
|
$6,003
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs