ITAC Assessment: MZ0264
ITAC logo
ITAC Assessment: MZ0264
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Aerospace Structural Components/Assemblies
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 30
Plant Area 28,000
ft2
Annual Production 70,000
lb
Production Hrs. Annual 3,003
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $41,931 487,648
kWh
Electricity Demand $18,751 1,690
kW-mo/yr
Electricity Fees $958 -
Natural Gas $8,137 861
MMBtu
TOTAL YEARLY COSTS $69,777
RECOMMENDED SAVINGS* $14,623 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,629

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings
01 2.6218: Turn off equipment when not in use $1,108 $2,050 $1,108
12,898
kWh
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,749 $1,328 $2,748
31,991
kWh
$1,421
-
kW-mo/yr
- $(-420.0)
03 2.8121: Apply for tax-free status for energy purchases $3,139 $1,050 - - $3,139 -
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,987 $1,460 - $1,987
-
kW-mo/yr
- -
05 2.7135: Install occupancy sensors $1,844 $710 $1,222
14,229
kWh
$622
-
kW-mo/yr
- -
06 2.2437: Recover waste heat from equipment $1,401 $810 $924
10,756
kWh
$477
-
kW-mo/yr
- -
07 2.4231: Reduce the pressure of compressed air to the minimum required $975 $836 $642
7,476
kWh
$333
-
kW-mo/yr
- -
08 2.4221: Install compressor air intakes in coolest locations $420 $274 $276
3,208
kWh
$144
-
kW-mo/yr
- -
TOTAL RECOMMENDED $14,623 $8,518 $6,920
80,558
kWh
$4,984
-
kW-mo/yr
$3,139 $(-420.0)
TOTAL IMPLEMENTED $7,629 $5,670 $2,026
23,582
kWh
$2,464
-
kW-mo/yr
$3,139 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs