Assessment Year | 2017 |
---|---|
Principal Product | Chrome plated bars and tubes |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
180,000
ft2
|
Annual Production | 15,000
units
|
Production Hrs. Annual | 8,000
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $553,469 | 10,211,600 |
kWh
|
$0.054 |
Electricity Demand | $449,469 | 31,366 |
kW-mo/yr
|
$14.33 |
Natural Gas | $72,759 | 9,771 |
MMBtu
|
$7.45 |
TOTAL YEARLY COSTS | $1,075,697 | |||
RECOMMENDED SAVINGS* | $163,451 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $162,645 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $7,020 | $6,000 | - | - |
$7,020
-
MMBtu
|
- | |
02 | 2.7135: Install occupancy sensors | $8,183 | $2,100 |
$5,346
99,100
kWh
|
$2,837
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,206 | $250 |
$5,206
96,404
kWh
|
- | - | - | |
04 | 2.4322: Use or replace with energy efficient substitutes | $806 | $5,500 |
$806
14,926
kWh
|
- | - | - | |
05 | 3.8124: Install floating covers on tanks of volatile materials to reduce evaporation | $7,139 | $5,400 | - | - |
$7,139
-
MMBtu
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $2,745 | $1,160 |
$2,745
50,830
kWh
|
- | - | - | |
07 | 2.3192: Use fossil fuel powered generator during peak demand periods | $119,328 | $208,000 |
$207,360
3,840,000
kWh
|
$137,568
-
kW-mo/yr
|
- |
$(-225,600.0)
-
MMBtu
|
|
08 | 2.4133: Use most efficient type of electric motors | $13,024 | $70,500 |
$8,510
157,500
kWh
|
$4,514
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $163,451 | $298,910 |
$229,973
4,258,760
kWh
|
$144,919
-
kW-mo/yr
|
$14,159
-
MMBtu
|
$(-225,600.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $162,645 | $293,410 |
$229,167
4,243,834
kWh
|
$144,919
-
kW-mo/yr
|
$14,159
-
MMBtu
|
$(-225,600.0)
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs