Assessment Year | 2001 |
---|---|
Principal Product | Compact Discs |
NAICS |
n/a
|
SIC | 3652: Phonograph Records and Prerecorded Audio Tapes and Disks |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
75,000
ft2
|
Annual Production | 37,440,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $471,171 | 8,980,219 |
kWh
|
$0.052 |
Electricity Demand | $116,205 | 12,995 |
kW-mo/yr
|
$8.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $405,469 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|
01 | 3.1191: Change procedures / equipment / operating conditions | $279,552 | $120 | - | - | $279,552 | |
02 | 2.5194: Redesign process | $24,074 | $13,312 |
$24,074
454,222
kWh
|
- | - | |
03 | 4.454: Modify startup/shutdown times | $14,899 | $139 | - |
$14,899
-
kW-mo/yr
|
- | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $48,965 | $16 |
$48,965
923,870
kWh
|
- | - | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $21,743 | $16 |
$21,743
410,243
kWh
|
- | - | |
06 | 2.7111: Reduce illumination to minimum necessary levels | $5,932 | $256 |
$4,763
89,856
kWh
|
$1,169
-
kW-mo/yr
|
- | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $10,304 | $256 |
$9,524
179,712
kWh
|
$780
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $405,469 | $14,115 |
$109,069
2,057,903
kWh
|
$16,848
-
kW-mo/yr
|
$279,552 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs