ITAC Assessment: MZ0213
ITAC logo
ITAC Assessment: MZ0213
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product switch gear
NAICS 335313: Switchgear and Switchboard Apparatus Manufacturing
SIC 3643: Current-Carrying Wiring Devices
Sales Range $10
M
to 50
M
# of Employees 222
Plant Area 164,000
ft2
Annual Production 12,000
units
Production Hrs. Annual 6,480
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $130,826 2,926,754
kWh
Electricity Demand $111,809 5,894
kW-mo/yr
Natural Gas $43,685 3,523
MMBtu
TOTAL YEARLY COSTS $286,320
RECOMMENDED SAVINGS* $48,245 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,815

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7135: Install occupancy sensors $1,940 $1,100 $1,940
43,400
kWh
- -
02 2.7221: Lower temperature during the winter season and vice-versa $29,759 $2,500 $6,560
146,760
kWh
$3,796
-
kW-mo/yr
$19,403
-
MMBtu
03 2.4221: Install compressor air intakes in coolest locations $3,111 $2,000 $1,745
39,041
kWh
$1,366
-
kW-mo/yr
-
04 2.7425: Clean or color roof to reduce solar load $11,560 $67,500 $6,476
144,888
kWh
$5,084
-
kW-mo/yr
-
05 2.4133: Use most efficient type of electric motors $1,875 $6,000 $1,875
41,950
kWh
- -
TOTAL RECOMMENDED $48,245 $79,100 $18,596
416,039
kWh
$10,246
-
kW-mo/yr
$19,403
-
MMBtu
TOTAL IMPLEMENTED $3,815 $7,100 $3,815
85,350
kWh
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs