ITAC Assessment: CO0665
ITAC logo
ITAC Assessment: CO0665
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Ready Mix Concrete
NAICS 327320: Ready-Mix Concrete Manufacturing
SIC 3273: Ready-Mixed Concrete
Sales Range $1
M
to 5
M
# of Employees 16
Plant Area 5,400
ft2
Annual Production 80,000
pieces
Production Hrs. Annual 3,432
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $13,699 358,000
kWh
Electricity Demand $34,311 1,698
kW-mo/yr
Electricity Fees $587 -
LPG $25,518 1,602
MMBtu
Fuel Oil #2 $39,667 1,851
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,370 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,650 $17,010 $660
17,100
kWh
$1,990
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,280 $1,600 $790
20,400
kWh
$1,490
-
kW-mo/yr
-
03 2.8121: Apply for tax-free status for energy purchases $1,310 $500 - - $1,310
04 2.6231: Utilize controls to operate equipment only when needed $1,790 $1,800 $710
18,400
kWh
$1,080
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $720 $2,840 $250
6,500
kWh
$470
-
kW-mo/yr
-
06 2.9114: Use solar heat to make electricty $2,620 $32,500 $550
14,100
kWh
$940
-
kW-mo/yr
$1,130
TOTAL RECOMMENDED $11,370 $56,250 $2,960
76,500
kWh
$5,970
-
kW-mo/yr
$2,440
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs