| Assessment Year | 2016 |
|---|---|
| Principal Product | polystyrene blocks |
| NAICS | 326140: Polystyrene Foam Product Manufacturing |
| SIC | 3086: Plastics Foam Products |
| Sales Range | $5 M to 10M |
| # of Employees | 47 |
| Plant Area |
72,000
ft2
|
| Annual Production | 50,000
ton
|
| Production Hrs. Annual | 8,250
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $52,201 | 580,020 |
kWh
|
$0.090 |
| Natural Gas | $81,346 | 11,621 |
MMBtu
|
$7.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $33,615 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $23,492 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $1,662 | $800 |
$1,662
18,464
kWh
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,883 | $14,300 |
$11,883
132,031
kWh
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $905 | $1,000 |
$905
10,054
kWh
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,076 | $960 |
$2,076
23,072
kWh
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,447 | $1,500 |
$1,447
16,080
kWh
|
- | |
| 06 | 2.2437: Recover waste heat from equipment | $553 | - |
$553
6,145
kWh
|
- | |
| 07 | 2.2511: Insulate bare equipment | $1,426 | - | - |
$1,426
-
MMBtu
|
|
| 08 | 2.7243: Improve air circulation with destratification fans / other methods | $6,461 | $4,950 |
$(-965.0)
(-10,725)
kWh
|
$7,426
-
MMBtu
|
|
| 09 | 2.7135: Install occupancy sensors | $902 | $560 |
$902
10,032
kWh
|
- | |
| 10 | 2.2121: Increase amount of condensate returned | $6,300 | $5,000 | - |
$6,300
-
MMBtu
|
|
| TOTAL RECOMMENDED | $33,615 | $29,070 |
$18,463
205,153
kWh
|
$15,152
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $23,492 | $21,820 |
$15,766
175,189
kWh
|
$7,726
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs