| Assessment Year | 2015 |
|---|---|
| Principal Product | food and pharmaceutical equipment |
| NAICS | 333241: Food Product Machinery Manufacturing |
| SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 70 |
| Plant Area |
32,500
ft2
|
| Annual Production | 500
pieces
|
| Production Hrs. Annual | 3,675
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $85,294 | 1,069,200 |
kWh
|
$0.080 |
| Electricity Demand | $30,752 | 3,844 |
kW-mo/yr
|
$8.00 |
| Natural Gas | $5,252 | 764 |
MMBtu
|
$6.87 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,750 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,654 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7232: Replace existing hvac unit with high efficiency model | $8,485 | $27,300 |
$6,901
86,504
kWh
|
$1,584
-
kW-mo/yr
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,482 | $3,430 |
$1,114
13,965
kWh
|
$368
-
kW-mo/yr
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,538 | $880 |
$1,914
23,989
kWh
|
$624
-
kW-mo/yr
|
|
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,096 | $1,500 |
$824
10,335
kWh
|
$272
-
kW-mo/yr
|
|
| 05 | 3.1161: Eliminate/reduce an operation | $149 | - |
$109
1,371
kWh
|
$40
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $13,750 | $33,110 |
$10,862
136,164
kWh
|
$2,888
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $12,654 | $31,610 |
$10,038
125,829
kWh
|
$2,616
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs