| Assessment Year | 2015 |
|---|---|
| Principal Product | aluminum die castings |
| NAICS | 331523: Nonferrous Metal Die-Casting Foundries |
| SIC | 3363: Aluminum Die-Castings |
| Sales Range | $10 M to 50M |
| # of Employees | 69 |
| Plant Area |
25,000
ft2
|
| Annual Production | 5,900,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $267,911 | 2,713,280 |
kWh
|
$0.099 |
| Natural Gas | $294,611 | 25,162 |
MMBtu
|
$11.71 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $91,028 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $88,295 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7492: Use proper thickness of insulation on building envelope | $21,804 | $700 | - |
$21,804
-
MMBtu
|
|
| 02 | 2.4221: Install compressor air intakes in coolest locations | $3,714 | $1,160 |
$3,714
37,512
kWh
|
- | |
| 03 | 2.2424: Use heat in flue gases to preheat products or materials | $62,777 | $37,500 | - |
$62,777
-
MMBtu
|
|
| 04 | 2.4239: Eliminate or reduce compressed air usage | $2,733 | $5,660 |
$2,733
27,331
kWh
|
- | |
| TOTAL RECOMMENDED | $91,028 | $45,020 |
$6,447
64,843
kWh
|
$84,581
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $88,295 | $39,360 |
$3,714
37,512
kWh
|
$84,581
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs