Assessment Year | 2015 |
---|---|
Principal Product | extruded rubber products |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3082: Unsupported Plastics Profile Shapes |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
102,000
ft2
|
Annual Production | 18,000
pieces
|
Production Hrs. Annual | 6,580
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $95,637 | 1,050,240 |
kWh
|
$0.091 |
Electricity Demand | $11,854 | 3,721 |
kW-mo/yr
|
$3.19 |
Natural Gas | $7,536 | 753 |
MMBtu
|
$10.01 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,273 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,619 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $2,801 | $1,160 |
$2,633
28,919
kWh
|
$168
-
kW-mo/yr
|
|
02 | 2.4239: Eliminate or reduce compressed air usage | $11,360 | $6,100 |
$11,360
126,226
kWh
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,247 | $920 |
$2,109
23,877
kWh
|
$138
-
kW-mo/yr
|
|
04 | 2.5122: Replace high resistance ducts, pipes, and fittings | $8,654 | $19,200 |
$8,130
90,335
kWh
|
$524
-
kW-mo/yr
|
|
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,211 | - |
$2,211
24,280
kWh
|
- | |
TOTAL RECOMMENDED | $27,273 | $27,380 |
$26,443
293,637
kWh
|
$830
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $18,619 | $8,180 |
$18,313
203,302
kWh
|
$306
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs