Assessment Year | 2015 |
---|---|
Principal Product | tires |
NAICS | 326211: Tire Manufacturing (except Retreading) |
SIC | 3011: Tires and Inner Tubes |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
380,000
ft2
|
Annual Production | 325,000
pieces
|
Production Hrs. Annual | 5,700
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $160,475 | 1,628,592 |
kWh
|
$0.099 |
Electricity Demand | $70,616 | 14,120 |
kW-mo/yr
|
$5.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $86,306 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,483 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.2314: Replace heat treating oven with more efficient unit | $36,633 | $120,000 |
$35,553
360,810
kWh
|
$1,080
-
kW-mo/yr
|
- | |
02 | 4.512: Condense operation into one building | $12,608 | - |
$11,393
115,625
kWh
|
$1,215
-
kW-mo/yr
|
- | |
03 | 4.122: Develop standard procedures to improve internal yields | $20,868 | $40,000 |
$17,027
172,800
kWh
|
$3,201
-
kW-mo/yr
|
$640 | |
04 | 2.4221: Install compressor air intakes in coolest locations | $2,095 | $3,500 |
$1,895
19,236
kWh
|
$200
-
kW-mo/yr
|
- | |
05 | 2.2437: Recover waste heat from equipment | $3,663 | $1,500 |
$3,663
37,220
kWh
|
- | - | |
06 | 3.1161: Eliminate/reduce an operation | $928 | - |
$838
8,504
kWh
|
$90
-
kW-mo/yr
|
- | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,483 | $860 |
$3,148
31,945
kWh
|
$335
-
kW-mo/yr
|
- | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,028 | $1,500 |
$6,028
61,172
kWh
|
- | - | |
TOTAL RECOMMENDED | $86,306 | $167,360 |
$79,545
807,312
kWh
|
$6,121
-
kW-mo/yr
|
$640 | ||
TOTAL IMPLEMENTED | $3,483 | $860 |
$3,148
31,945
kWh
|
$335
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs