ITAC Assessment: MZ0141
ITAC logo
ITAC Assessment: MZ0141
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product frozen dough
NAICS 311812: Commercial Bakeries
SIC 2045: Prepared Flour Mixes and Doughs
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 450,000
ft2
Annual Production 24,000,000
units
Production Hrs. Annual 8,600
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,481,084 31,677,111
kWh
Electricity Demand $728,483 63,904
kW-mo/yr
Natural Gas $255,499 55,240
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $72,170 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,083

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7425: Clean or color roof to reduce solar load $2,625 $7,000 $2,180
27,836
kWh
$445
-
kW-mo/yr
-
02 2.7292: Lower ceiling to reduce conditioned space $12,947 $24,000 $11,750
150,067
kWh
$1,197
-
kW-mo/yr
-
03 2.2437: Recover waste heat from equipment $3,254 $11,500 - - $3,254
-
MMBtu
04 2.2437: Recover waste heat from equipment $4,000 $6,000 - - $4,000
-
MMBtu
05 2.4221: Install compressor air intakes in coolest locations $11,440 $2,500 $9,533
121,752
kWh
$1,907
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $23,518 $21,850 $19,545
249,615
kWh
$3,973
-
kW-mo/yr
-
07 2.7135: Install occupancy sensors $10,446 $1,875 $10,446
133,412
kWh
- -
08 2.7221: Lower temperature during the winter season and vice-versa $3,940 - $3,275
41,832
kWh
$665
-
kW-mo/yr
-
TOTAL RECOMMENDED $72,170 $74,725 $56,729
724,514
kWh
$8,187
-
kW-mo/yr
$7,254
-
MMBtu
TOTAL IMPLEMENTED $30,083 $28,850 $25,000
319,283
kWh
$5,083
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs