ITAC Assessment: MA0400
ITAC logo
ITAC Assessment: MA0400
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Plating
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range n/a
# of Employees 66
Plant Area 56,898
ft2
Annual Production 0
units
Production Hrs. Annual 8,112
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $125,365 2,576,788
kWh
Electricity Demand $96,168 5,796
kW-mo/yr
Natural Gas $138,984 31,096
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $381,869 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,065

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (haz) Savings Administrative Changes Savings Primary Raw Material Savings Water Consumption Savings
01 3.4111: Use closed cycle process to minimize waste water production $347,702 $505,000 - - - $84,300
-
lb
- $182,321 $81,081
-
Tgal
02 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $17,497 $92,676 $85,388
2,589,977
kWh
$67,536
-
kW-mo/yr
$(-42,751.0)
-
MMBtu
- $(-92,676.0) - -
03 2.2514: Cover open tanks $15,677 $6,578 - - $15,677
-
MMBtu
- - - -
04 2.2511: Insulate bare equipment $605 $970 $17
586
kWh
- $588
-
MMBtu
- - - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $388 - $388
14,361
kWh
- - - - - -
TOTAL RECOMMENDED $381,869 $605,224 $85,793
2,604,924
kWh
$67,536
-
kW-mo/yr
$(-26,486.0)
-
MMBtu
$84,300
-
lb
$(-92,676.0) $182,321 $81,081
-
Tgal
TOTAL IMPLEMENTED $16,065 $6,578 $388
14,361
kWh
- $15,677
-
MMBtu
- - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs