Assessment Year | 2014 |
---|---|
Principal Product | brake cables |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
132,000
ft2
|
Annual Production | 50,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $195,604 | 2,772,468 |
kWh
|
$0.071 |
Electricity Demand | $20,592 | 9,131 |
kW-mo/yr
|
$2.26 |
Natural Gas | $81,920 | 8,551 |
MMBtu
|
$9.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,567 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,638 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $1,036 | - |
$946
13,320
kWh
|
$90
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $1,989 | $1,920 |
$1,989
28,015
kWh
|
- | - | |
03 | 2.4234: Cool compressor air intake with heat exchanger | $856 | $2,050 |
$781
11,000
kWh
|
$75
-
kW-mo/yr
|
- | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $16,610 | - |
$4,200
59,157
kWh
|
$334
-
kW-mo/yr
|
$12,076
-
MMBtu
|
|
05 | 2.2437: Recover waste heat from equipment | $805 | $1,475 | - | - |
$805
-
MMBtu
|
|
06 | 2.7442: Keep doors and windows shut when not on use | $8,378 | - | - | - |
$8,378
-
MMBtu
|
|
07 | 2.7229: Air condition only space necessary | $4,215 | - | - | - |
$4,215
-
MMBtu
|
|
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,678 | $7,200 |
$4,678
65,881
kWh
|
- | - | |
TOTAL RECOMMENDED | $38,567 | $12,645 |
$12,594
177,373
kWh
|
$499
-
kW-mo/yr
|
$25,474
-
MMBtu
|
||
TOTAL IMPLEMENTED | $28,638 | $5,445 |
$6,970
98,172
kWh
|
$409
-
kW-mo/yr
|
$21,259
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs