ITAC Assessment: LM0022
ITAC logo
ITAC Assessment: LM0022
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product aerospace metal ducts
NAICS
n/a
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area 125,000
ft2
Annual Production 163,285
pieces
Production Hrs. Annual 5,246
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $127,553 2,498,389
kWh
Electricity Demand $97,945 18,780
kW-mo/yr
Electricity Fees $99,769 -
Natural Gas $67,862 8,427
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $143,637 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $112,781

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Primary Product Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,734 $100 $2,093
18,472
kWh
$421
-
kW-mo/yr
$(-780.0) - -
02 2.4221: Install compressor air intakes in coolest locations $2,848 $164 $2,371
20,931
kWh
$477
-
kW-mo/yr
- - -
03 2.3134: Shift from daytime to nighttime operation $54,047 $450 $26,813
235,000
kWh
$60,984
-
kW-mo/yr
$(-33,750.0) - -
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $28,008 $15,300 - - - $28,008 -
05 4.611: Begin a practice of predictive / preventative maintenance $57,000 $102,000 - - $(-78,000.0) - $135,000
TOTAL RECOMMENDED $143,637 $118,014 $31,277
274,403
kWh
$61,882
-
kW-mo/yr
$(-112,530.0) $28,008 $135,000
TOTAL IMPLEMENTED $112,781 $102,550 $28,906
253,472
kWh
$61,405
-
kW-mo/yr
$(-112,530.0) - $135,000
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs