Assessment Year | 2013 |
---|---|
Principal Product | Beverages |
NAICS | 311422: Specialty Canning |
SIC | 2032: Canned Specialties |
Sales Range | $100 M to 500M |
# of Employees | 170 |
Plant Area |
232,000
ft2
|
Annual Production | 288,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $541,778 | 13,498,824 |
kWh
|
$0.040 |
Electricity Demand | $392,682 | 32,771 |
kW-mo/yr
|
$11.98 |
Natural Gas | $848,410 | 209,127 |
MMBtu
|
$4.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $169,704 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $52,542 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1212: Operate boilers on high fire setting | $67,232 | $111,000 | - | - |
$67,232
-
MMBtu
|
- | - | - | - | |
02 | 2.2121: Increase amount of condensate returned | $28,581 | $40,000 | - | - |
$22,184
-
MMBtu
|
- |
$2,340
-
gal
|
- | $4,057 | |
03 | 2.2437: Recover waste heat from equipment | $28,256 | $4,000 | - | - |
$28,256
-
MMBtu
|
- | - | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,620 | $3,100 |
$5,404
134,762
kWh
|
$2,216
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,108 | $1,630 |
$4,445
111,129
kWh
|
$2,663
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.2437: Recover waste heat from equipment | $5,895 | $2,000 | - | - |
$5,895
-
MMBtu
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,152 | $12,430 |
$3,223
80,362
kWh
|
$1,929
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.1241: Reduce excessive boiler blowdown | $4,877 | $2,600 | - | - |
$3,393
-
MMBtu
|
$1,287
-
Tgal
|
$197
-
gal
|
- | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,603 | $3,100 |
$2,561
63,896
kWh
|
$1,042
-
kW-mo/yr
|
- | - | - | - | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $3,050 | $925 |
$1,912
47,687
kWh
|
$1,138
-
kW-mo/yr
|
- | - | - | - | - | |
11 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,911 | $1,030 |
$1,821
45,534
kWh
|
$1,090
-
kW-mo/yr
|
- | - | - | - | - | |
12 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,198 | - |
$1,306
32,564
kWh
|
$892
-
kW-mo/yr
|
- | - | - | - | - | |
13 | 2.7135: Install occupancy sensors | $1,565 | $640 |
$978
24,391
kWh
|
$587
-
kW-mo/yr
|
- | - | - | - | - | |
14 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $865 | $635 | - | - |
$865
-
MMBtu
|
- | - | - | - | |
15 | 2.1233: Analyze flue gas for proper air/fuel ratio | $791 | $1,000 | - | - |
$881
-
MMBtu
|
- | - | $(-90.0) | - | |
TOTAL RECOMMENDED | $169,704 | $184,090 |
$21,650
540,325
kWh
|
$11,557
-
kW-mo/yr
|
$128,706
-
MMBtu
|
$1,287
-
Tgal
|
$2,537
-
gal
|
$(-90.0) | $4,057 | ||
TOTAL IMPLEMENTED | $52,542 | $62,035 |
$11,207
279,778
kWh
|
$6,221
-
kW-mo/yr
|
$27,323
-
MMBtu
|
$1,287
-
Tgal
|
$2,537
-
gal
|
$(-90.0) | $4,057 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs