| Assessment Year | 2013 |
|---|---|
| Principal Product | shampoo, personal care products |
| NAICS | 325620: Toilet Preparation Manufacturing |
| SIC | 2844: Perfumes, Cosmetics, and Other Toilet Preparations |
| Sales Range | $50 M to 100M |
| # of Employees | 250 |
| Plant Area |
600,000
ft2
|
| Annual Production | 459,173,064
pieces
|
| Production Hrs. Annual | 8,520
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,393,003 | 23,623,200 |
kWh
|
$0.059 |
| Electricity Demand | $120 | 12 |
kW-mo/yr
|
$10.00 |
| Natural Gas | $183,557 | 96,634 |
MMBtu
|
$1.90 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $242,550 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $100,799 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $0.0 | - |
$0.0
1
kWh
|
- | - | - | |
| 02 | 2.7135: Install occupancy sensors | $13,741 | $16,000 |
$13,741
232,900
kWh
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $57,890 | $57,890 |
$46,734
792,104
kWh
|
$11,156
-
kW-mo/yr
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,446 | $1,300 |
$5,204
88,214
kWh
|
$1,242
-
kW-mo/yr
|
- | - | |
| 05 | 2.7221: Lower temperature during the winter season and vice-versa | $5,595 | - |
$2,606
44,166
kWh
|
$605
-
kW-mo/yr
|
$2,384
-
MMBtu
|
- | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $17,597 | $8,000 |
$14,219
241,004
kWh
|
$3,378
-
kW-mo/yr
|
- | - | |
| 07 | 2.2437: Recover waste heat from equipment | $3,278 | $4,500 | - | - |
$3,278
-
MMBtu
|
- | |
| 08 | 2.2692: Use outside cold water source as a supply of cooling water | $55,500 | $650,000 |
$12,000
203,390
kWh
|
$6,000
-
kW-mo/yr
|
$37,500
-
MMBtu
|
- | |
| 09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $0.0 | - | - | - | - | $0.0 | |
| 10 | 2.2414: Use waste heat from hot flue gases to preheat | $9,000 | - | - | - |
$9,000
-
MMBtu
|
- | |
| 11 | 2.2113: Repair or replace steam traps | $12,000 | - | - | - |
$12,000
-
MMBtu
|
- | |
| 12 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $38,737 | $28,800 |
$38,737
656,554
kWh
|
- | - | - | |
| 13 | 2.4133: Use most efficient type of electric motors | $22,766 | $60,580 |
$18,307
310,289
kWh
|
$4,459
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $242,550 | $827,070 |
$151,548
2,568,622
kWh
|
$26,840
-
kW-mo/yr
|
$64,162
-
MMBtu
|
$0.0 | ||
| TOTAL IMPLEMENTED | $100,799 | $58,600 |
$71,901
1,218,673
kWh
|
$4,620
-
kW-mo/yr
|
$24,278
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs