ITAC Assessment: MZ0116
ITAC logo
ITAC Assessment: MZ0116
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product large centrifugal pumps and compressors
NAICS 333912: Air and Gas Compressor Manufacturing
SIC 3563: Air and Gas Compressors
Sales Range $10
M
to 50
M
# of Employees 14
Plant Area 60,000
ft2
Annual Production 500
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $62,742 848,842
kWh
Electricity Demand $16,040 7,487
kW-mo/yr
Natural Gas $14,942 2,010
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,190 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7134: Use photocell controls $2,023 $900 $2,023
27,332
kWh
- -
02 2.7221: Lower temperature during the winter season and vice-versa $10,131 - $6,182
83,542
kWh
$245
-
kW-mo/yr
$3,704
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $890 $1,000 $765
10,340
kWh
$125
-
kW-mo/yr
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $11,715 $93,750 $11,715
158,312
kWh
- -
05 2.4221: Install compressor air intakes in coolest locations $1,431 $1,160 $1,230
16,619
kWh
$201
-
kW-mo/yr
-
TOTAL RECOMMENDED $26,190 $96,810 $21,915
296,145
kWh
$571
-
kW-mo/yr
$3,704
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs