Assessment Year | 1996 |
---|---|
Principal Product | Electronic Components |
NAICS |
n/a
|
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 500 |
Plant Area |
185,000
ft2
|
Annual Production | 200,000
pieces
|
Production Hrs. Annual | 4,080
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $180,465 | 10,209,555 |
kWh
|
$0.018 |
Electricity Demand | $286,664 | 21,545 |
kW-mo/yr
|
$13.31 |
Electricity Fees | $234,170 | - |
|
- |
Natural Gas | $121,489 | 35,387 |
MMBtu
|
$3.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $87,147 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,719 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,378 | $6,136 |
$9,378
136,577
kWh
|
- | - | - | - | |
02 | 2.2612: Use cooling tower water instead of refrigeration | $24,554 | $66,950 |
$24,554
362,251
kWh
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,848 | $8,027 |
$4,533
256,155
kWh
|
$10,315
-
kW-mo/yr
|
- | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $2,690 | $2,976 |
$886
50,117
kWh
|
$1,804
-
kW-mo/yr
|
- | - | - | |
05 | 2.4131: Size electric motors for peak operating efficiency | $8,786 | $1,296 |
$4,329
244,725
kWh
|
$4,457
-
kW-mo/yr
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $465 | $400 |
$465
26,377
kWh
|
- | - | - | - | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,400 | $500 | - | - |
$1,400
-
MMBtu
|
- | - | |
08 | 2.2414: Use waste heat from hot flue gases to preheat | $9,088 | $7,873 | - | - |
$9,088
-
MMBtu
|
- | - | |
09 | 3.6192: Use a less expensive method of waste removal | $15,938 | - | - | - | - |
$1,200
-
lb
|
$14,738
-
lb
|
|
TOTAL RECOMMENDED | $87,147 | $94,158 |
$44,145
1,076,202
kWh
|
$16,576
-
kW-mo/yr
|
$10,488
-
MMBtu
|
$1,200
-
lb
|
$14,738
-
lb
|
||
TOTAL IMPLEMENTED | $22,719 | $11,308 |
$15,058
457,796
kWh
|
$6,261
-
kW-mo/yr
|
$1,400
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs