Assessment Year | 2013 |
---|---|
Principal Product | pharmaceuticals |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 5122: Drugs, Drug Proprietaries, and Druggists' Sundries |
Sales Range | $100 M to 500M |
# of Employees | 259 |
Plant Area |
494,000
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $220,684 | 2,929,200 |
kWh
|
$0.075 |
Electricity Demand | $23,388 | 7,619 |
kW-mo/yr
|
$3.07 |
Natural Gas | $25,937 | 3,225 |
MMBtu
|
$8.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $84,317 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $19,287 | $11,200 |
$5,573
69,660
kWh
|
$713
-
kW-mo/yr
|
$13,001
-
MMBtu
|
|
02 | 2.7496: Install partitions to reduce size of conditioned space | $14,164 | $10,000 |
$13,930
190,821
kWh
|
$234
-
kW-mo/yr
|
- | |
03 | 2.2622: Replace existing chiller with high efficiency model | $50,867 | $155,000 |
$27,952
349,410
kWh
|
$22,915
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $84,317 | $176,200 |
$47,455
609,891
kWh
|
$23,861
-
kW-mo/yr
|
$13,001
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs