| Assessment Year | 2012 |
|---|---|
| Principal Product | solvents, resins, monomers |
| NAICS | 236210: Industrial Building Construction |
| SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
| Sales Range | $10 M to 50M |
| # of Employees | 272 |
| Plant Area |
128,119
ft2
|
| Annual Production | 350
ton
|
| Production Hrs. Annual | 3,650
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $473,476 | 7,066,804 |
kWh
|
$0.067 |
| Electricity Demand | $9 | 1 |
kW-mo/yr
|
$8.50 |
| Natural Gas | $114,281 | 10,446 |
MMBtu
|
$10.94 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $211,394 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $65,583 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,823 | $28,300 |
$9,049
135,057
kWh
|
$3,774
-
kW-mo/yr
|
- | - | |
| 02 | 2.2621: Modify refrigeration system to operate at a lower pressure | $42,257 | $4,645 |
$42,257
630,720
kWh
|
- | - | - | |
| 03 | 2.2442: Preheat combustion air with waste heat | $12,339 | $13,500 | - | - |
$12,339
-
MMBtu
|
- | |
| 04 | 2.6127: Maintain air filters by cleaning or replacement | $8,215 | $52,200 |
$8,215
122,612
kWh
|
- | - | - | |
| 05 | 2.7135: Install occupancy sensors | $58,099 | $39,870 |
$58,099
867,153
kWh
|
- | - | - | |
| 06 | 2.2692: Use outside cold water source as a supply of cooling water | $42,514 | $318,000 |
$34,248
511,165
kWh
|
- |
$8,266
-
MMBtu
|
- | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $920 | $1,160 |
$649
9,688
kWh
|
$271
-
kW-mo/yr
|
- | - | |
| 08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $30,462 | $115,696 |
$21,496
320,835
kWh
|
$8,966
-
kW-mo/yr
|
- | - | |
| 09 | 3.4114: Replace city water with recycled water via cooling tower | $2,288 | $2,000 | - | - | - |
$2,288
-
Tgal
|
|
| 10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,476 | $1,140 |
$1,476
22,035
kWh
|
- | - | - | |
| 11 | 4.431: Train operators for maximum operating efficiency | $1 | $1 |
$1
1
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $211,394 | $576,512 |
$175,490
2,619,266
kWh
|
$13,011
-
kW-mo/yr
|
$20,605
-
MMBtu
|
$2,288
-
Tgal
|
||
| TOTAL IMPLEMENTED | $65,583 | $87,145 |
$59,521
888,389
kWh
|
$3,774
-
kW-mo/yr
|
- |
$2,288
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs