Assessment Year | 2012 |
---|---|
Principal Product | Rubber & Plastics Hose & Belting |
NAICS | 326220: Rubber and Plastics Hoses and Belting Manufacturing |
SIC | 3052: Rubber and Plastics Hose and Belting |
Sales Range | $50 M to 100M |
# of Employees | 195 |
Plant Area |
293,000
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $201,251 | 2,886,000 |
kWh
|
$0.070 |
Electricity Demand | $20,901 | 7,394 |
kW-mo/yr
|
$2.83 |
Natural Gas | $97,908 | 10,735 |
MMBtu
|
$9.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,867 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,933 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $1,105 | $1,160 |
$1,025
14,647
kWh
|
$80
-
kW-mo/yr
|
- | |
02 | 2.4223: Install direct acting units in place of compressed air pressure system in safety system | $934 | $4,969 |
$737
10,533
kWh
|
$196
-
kW-mo/yr
|
- | |
03 | 2.2437: Recover waste heat from equipment | $6,340 | $8,800 | - | - |
$6,340
-
MMBtu
|
|
04 | 2.2511: Insulate bare equipment | $199 | $297 | - | - |
$199
-
MMBtu
|
|
05 | 2.2136: Install / repair insulation on steam lines | $290 | $360 | - | - |
$290
-
MMBtu
|
|
TOTAL RECOMMENDED | $8,867 | $15,586 |
$1,763
25,180
kWh
|
$276
-
kW-mo/yr
|
$6,829
-
MMBtu
|
||
TOTAL IMPLEMENTED | $7,933 | $10,617 |
$1,025
14,647
kWh
|
$80
-
kW-mo/yr
|
$6,829
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs