ITAC Assessment: MZ0095
ITAC logo
ITAC Assessment: MZ0095
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Aluminum castings
NAICS 331524: Aluminum Foundries (except Die-Casting)
SIC 3365: Aluminum Foundries
Sales Range less than $500
k
# of Employees 14
Plant Area 16,000
ft2
Annual Production 89,562
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $63,670 675,300
kWh
Electricity Demand $16,534 3,045
kW-mo/yr
Natural Gas $2,351 241
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,969 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,021

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4221: Install compressor air intakes in coolest locations $199 $640 $149
1,579
kWh
$49
-
kW-mo/yr
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,134 $5,290 $852
9,011
kWh
$282
-
kW-mo/yr
03 2.6241: Reduce temperature of process equipment when on standby $688 - $688
7,282
kWh
-
04 2.1121: Use insulation in furnaces to facilitate heating / cooling $7,949 $1,660 $7,949
83,670
kWh
-
TOTAL RECOMMENDED $9,969 $7,590 $9,638
101,542
kWh
$332
-
kW-mo/yr
TOTAL IMPLEMENTED $2,021 $5,930 $1,689
17,872
kWh
$332
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs